The Bale Barn

Homer, Alaska

 In Progress

(Updated November, 2002)

This building is not finished, but I'm working on it.  It was begun in the spring of 2001 in Homer, Alaska.  The idea was to build a workshop out of local and recycled materials that was well insulated, low cost, and architecturally pleasing.  What I came up with is essentially a nine sided (nonagon) pole barn, with baled shredded paper as infill in the walls, and a 3 sided cupola offset to the north side.  The poles came from trees that I cut on our property.  The trees have been dead for 4 to 6 years as a result of a spruce bark beetle infestation here.  The lumber mostly came from these trees as well.  I cut, limbed, loaded, and hauled the trees to a local saw mill to be turned into lumber for this project.  This was a significant amount of labor, but I feel very good about using the trees from the site to build with.   Several of the trees cut were trees that could have fallen on the building site.  The local saw mill does very fine work, and the rough cut 4x12 beams supporting the cupola will remain exposed on the inside of the workshop area.  This will hopefully add a nice contrast to the plastered walls.  The poles will be buried in the walls, each wall section containing 9 bales.  The bales are 32" long x 24" wide x 18" high, and weigh about 125 pounds.  They are stacked on edge in the wall sections, on the stringers secured to each pole, creating an 8 foot wide by 6 foot high by 18" thick bale panel between each pole.  The stringer solution came about in an effort to reduce the foundation work, and to keep the bales up off of the ground.  An insulated skirting will extend from the bale walls down to the finished grade.  The floor will be of wood chips, possibly insulated beneath with blue board, and the ceiling will be insulated with blown-in shredded newsprint.  This nonagon is a prototype for the paper bale building technique, a possible parallel to straw bale construction in regions where there is abundant waste paper but little straw.  The paper bales' biggest drawback is their weight, other than that they generally seem to work well.  Thanks to my partner Sharon for her help and support, and to our friends who have helped along the way.

I welcome your comments.

Dale Banks

  loopy@homernet.net

 

 

6.1.1 beginning pile.JPG (203700 bytes)  6/1/1  In the beginning, there were trees...

6.1.1 The beginning.JPG (205804 bytes)  6/1/1 And open space...

7.02.01 Big yellow loads logs.JPG (149911 bytes)  7/2/1  Then some trees were cut, limbed, and loaded up for milling.

7.28.01 Dale chars pole.JPG (153086 bytes)  7/28/1  Smaller trees and ends were used for poles.  The poles were de-barked and charred.

7.28.01 Dale footers.JPG (167704 bytes)  7/28/1  Holes were dug 3 feet plus, and footers were made of concrete.

7.28.01 Hailey pours footers.JPG (181431 bytes)  7/28/1  The shoveling was tough work.

7.29.01 bituitene on charred pole.JPG (182838 bytes)  7/29/1  Poles were wrapped with bitch-a-thane (ice and water shield) from 1 foot below to 1 foot above ground level.

7.29.01 Sharon leans.JPG (200888 bytes)  7/29/1  More digging and leaning.

7.29.01 some small poles up.JPG (178376 bytes)  7/29/1  Some poles in the ground.

8.1.1 pole raising1.JPG (122109 bytes)  8/1/1  Pole raising - almost there.

8.1.1 hooray pole is up.JPG (133656 bytes)  8/1/1  Got it.

8.12.1 Stringers.JPG (162948 bytes)  8/12/1  Some stringers are up.

8.12.1 Test wall.JPG (130736 bytes)  8/12/1  Bales of paper will rest on the stringers between poles.

8.13.01 cupola beam.JPG (175695 bytes)  8/13/1  The first beam for the cupola.

8.13.1 Dale on beam.JPG (182942 bytes)  8/13/1  Finally, some rest.

8.15.01 cupola beams up.JPG (126439 bytes)  8/15/1  3 beams up.

9.4.01 South roof .JPG (176365 bytes)  9/4/1  The beginnings of a roof.

9.4.1 South roof detail.JPG (145162 bytes)  9/4/1  Roof framing detail.

9.8.01 cupola walls go up.JPG (159955 bytes)  9/8/1  Cupola walls are framed.

9.9.01 Hailey helps.JPG (168895 bytes)  9/9/1  A good helper.

9.10.01 cupola walls and east roof.JPG (174140 bytes)  9/10/1  Cupola walls and East roofs.

Dscf0303.jpg (84355 bytes)  9/25/1 Roof Framing.

Dscf0304.jpg (88043 bytes)  9/25/1 Lower roof deck finished.

Dscf0319.jpg (90723 bytes)  9/30/1 Roof with roofing felt.  Arched Garage door entry.

Dscf0325.jpg (90904 bytes)  10/7/1  Rolled asphalt roofing application.  Hip rafters up.

Dscf0327.jpg (89167 bytes)  10/8/1  View from the house porch.

Dscf0395.jpg (334495 bytes)  11/16/1  House wrap, cupola roof framed and mostly decked.

Dscf0398.jpg (86548 bytes)  11/16/1  From West side.

Dscf0399.jpg (158477 bytes)  11/16/1  Wall section before bales.

11.23.01 Sharon inspects the bales.jpg (301460 bytes)  11/23/1 Sharon inspects the bales.

11.23.01 First bale wall section.jpg (320205 bytes)  11/23/1 The first bale wall section is up.

Dscf0006.jpg (343527 bytes)  11/24/1  The pile of bales in the morning.

Dscf0008.jpg (354214 bytes)  11/24/1  The pile gets smaller.

Dscf0011.jpg (325150 bytes)  11/24/1  Putting the bales in place.

Dscf0021.jpg (319480 bytes)  11/25/1  A new look.

Dscf0022.jpg (316000 bytes)  11/25/1  Mostly baled walls.

2002_0607_111625AA.JPG (360008 bytes)  6/7/2002 Let the plastering begin.  

2002_0607_115857AA.JPG (333613 bytes)  6/7/2  The first 10 square feet applied.

2002_0616_093459AA.JPG (347745 bytes)  6/16/2 Sophie mixes the earthen plaster

2002_0616_102035AAsmall.JPG (223859 bytes)  6/16/2  Hailey likes this stuff.

2002_0705_211832AA.JPG (159059 bytes)  7/5/2  The first wall finished!

2002_0706_193441AA.JPG (175366 bytes)  7/6/2002  Friends help apply the mud.

2002_0707_185520AA.JPG (196446 bytes)  7/7/2002  More happy helpers.

2002_0708_112610AA.JPG (179536 bytes)  7/8/2002  From the West.

2002_0716_075329AA.JPG (228831 bytes)  7/16/2002  The mortar mixer, sawdust pile, clay/sand pile.

2002_0716_075545AA.JPG (109581 bytes)  7/16/2002  Interior walls can be the artist's canvas.

2002_0730_220656AA.JPG (141584 bytes)  7/30/2002  The Truth Window

2002_0815_181913AA.JPG (167112 bytes)  8/15/2002  All walls have been plastered.  Some mixed width spruce siding begun on the cupola.  Still needs a door built for the large car sized opening.

2002_1116_110216AA.JPG (92203 bytes)  11/16/2002 Finally the cupola is sided, a temporary garage door is tacked on, and the snows have started.

As of September, 2002, all exterior and interior walls have been plastered, and the plaster has dried.  There were some small cracks and we went back with a clay/sand mix to fill them in.   We bought a mortar mixer which seems to be the perfect tool for mixing the batches of plaster.  We used local clay, sand, lawnmower chopped straw, sawmill shavings, and wheat paste in the batches for the exterior.  In October, 2002, the wall between the two doors got hit pretty hard with driving rain.  The plaster held up well, with little erosion.  Some areas were still wet when the temperature dropped below freezing, so there are some frozen spots in the plaster.  No cracking, flaking, or other damage is noticeable yet.

 

 

Hit Counter